1
我有以下項目時間表。我需要從開始會議的第一名開始wbs。 直到開球,我使用了定製的wbs碼,即M1,M2,M3,M4。這是工作。 從由啓動會議上病房我需要開始1 1.1 1.2 2,2.1,2.2等等ms項目:wbs編號重置問題
現有時間表
WBS Task name
1 M1: Milestone1
2 M2: Milestone2
3 M3: Milestone3
4 M4: Milestone4
5 Kick-off meeting
6 Requirement
6.1. Requirement collection
6.2. Requirement priority
6.3. Finalise requirements
7 Design
7.1 High level design
7.2 Low level design
8 Implementation
8.1 coding
8.2 code review
9 Testing
9.1 Test plan
9.2 Test case preparation
9.3 Start Testing
10 Delivery
10.1 Deliver to customer
10.2 Release resource
我需要如以下WBS代碼來更改上述WBS。
預計時間表
WBS Task name
M1: Milestone1
M2: Milestone2
M3: Milestone3
M4: Milestone4
1 Kick-off meeting
2 Requirement
2.1. Requirement collection
2.2. Requirement priority
2.3. Finalise requirements
3 Design
3.1 High level design
3.2 Low level design
4 Implementation
4.1 coding
4.2 code review
5 Testing
5.1 Test plan
5.2 Test case preparation
5.3 Start Testing
6 Delivery
6.1 Deliver to customer
6.2 Release resource
我試圖與項目 - > WBS - >定義代碼和重新編號。兩者都不起作用。請幫忙。提前致謝。