流程編輯我認爲它這樣做是在默認情況下 - 至少在它的MSF敏捷5.0流程模板的任務。

總之,你需要的是從主動到封閉式過渡複製一些價值觀和並清空剩餘工作的規則:

<TRANSITION from="Active" to="Closed"> 
    <!--Reasons snipped --> 
    <FIELDS> 
     <!--Other fields snipped --> 
     <FIELD refname="Microsoft.VSTS.Scheduling.RemainingWork"> 
      <EMPTY /> 
     </FIELD> 
     <FIELD refname="Microsoft.VSTS.Scheduling.OriginalEstimate"> 
      <WHEN field="Microsoft.VSTS.Scheduling.OriginalEstimate" value=""> 
      <COPY from="field" field="Microsoft.VSTS.Scheduling.CompletedWork" /> 
      </WHEN> 
     </FIELD> 
     <FIELD refname="Microsoft.VSTS.Scheduling.CompletedWork"> 
      <WHEN field="Microsoft.VSTS.Scheduling.CompletedWork" value=""> 
      <COPY from="field" field="Microsoft.VSTS.Scheduling.OriginalEstimate" /> 
      </WHEN> 
     </FIELD> 
    </FIELDS> 
</TRANSITION> 